All markets

Mozambique

With a cumulative score of 1.28, Mozambique ranks number 75 among emerging markets and number 104 in the global ranking.

  • Emerging markets
  • Middle East & Africa

1.56 / 5

Power score


0.62 / 5

Transport score


 

Buildings score


Only 56 markets (28 emerging markets) are scored on the Buildings sector. See the full list on the methodology page.


Compare

Low-carbon strategy

Net-zero goal and strategy

Mozambique does not yet have a net-zero emissions target.

Nationally Determined Contributions (NDC)

The country submitted its updated Nationally Determined Contribution (NDC) – its plan to achieve the goals set out in the Paris Agreement – to the United Nations Framework Convention on Climate Change (UNFCCC) in November 2021. This lays out an ambition to lower greenhouse gas emissions by 40 million metric tons of CO2 equivalent (tCO2e) from 2020 to 2025 versus a business-as-usual scenario, excluding the contribution of afforestation efforts. The NDC states this would equate to a mitigation of 1.2tCO2e per capita by 2025, which is more than half of current per capita emissions of 2tCO2e.

Fossil fuel phase-out policy

Mozambique does not have a fossil-fuel phase-out policy.

Power

Power policy

Mozambique’s National Electrification Strategy encompasses its plan to prioritize investment in the development of lower-cost power infrastructure and draws up a strategy to connect new consumers with distribution networks. Early steps were toward developing clean energy and financial support for projects. While longer-term priorities include large hydroelectric power projects, such as the 1,500-megawatt (MW) Mphanda Nkuwa dam, nearer-term efforts are focused on fossil-fuel facilities and two solar projects, one of which was commissioned in July 2019.

Scatec's 40MW Mocuba PV plant is the country’s first utility-scale solar project. A second, Neoen's 40-megawatt Metoro PV Plant, is still under development.

Under Mozambique’s New and Renewable Energy Development Strategy for 2011-2025, the country plans to install 100MW of on-grid onshore wind capacity, up to 10,000 onshore wind turbines for off-grid generation, and approximately 125MW of small hydro.

The Ministry of Energy published a long-term development strategy, called the Integrated Electricity Infrastructure Master Plan, in 2018. It envisions new power generation projects totaling 530MW of solar and 150MW of wind, in addition to 4,300MW of hydro, 1,350MW of coal and 8,500MW of natural gas.

Power policies

Renewable energy auction
Feed-in Tariff
Import tax incentives
Net Metering
Renewable energy target
VAT incentives

Power prices and costs

Following a five-year freeze from 2010-15, retail power prices have risen considerably in recent years. Commercial tariffs increased 49% and residential bills more than doubled across 2016-2021 as state utility Electricidade de Mocambique (EDM) attempts to make up for longstanding revenue shortfalls. In 2021, the regulator kept tariffs for both industrial and residential bands flat. Social tariffs, which apply to low-income users, have remained stable.

Loading...

Power market

Mozambique’s power market is structured around EDM, a state-owned and vertically integrated utility responsible for the transmission, distribution and sale of electricity. All power consumers in Mozambique must buy electricity from EDM, which oversees 20% of the country’s generating capacity and purchases power from independent power producers and the 2.1-gigawatt Cahora Bassa hydropower plant.

Cahora Bassa is majority state-owned and 90% of its generation is exported, mostly to South Africa. The plant’s vast size means hydroelectric generation dominates Mozambique’s power sector, representing 74% of the capacity mix in 2021.

Like most countries in Sub-Saharan Africa, Mozambique does not have a wholesale power market, but it belongs to the Southern Africa Power Pool ¬– an electricity power pool that spans 12 countries in the region – which is gradually increasing liquidity.

A new draft electricity law is expected to overhaul Mozambique’s power sector, streamlining the legal framework and clarifying licensing for generation, transmission and distribution. A new regulator, Arene, was established in 2017 but is not yet fully operational and will require support to become a strong and independent regulatory body.

Installed Capacity (in MW)

2012201420162018202001K2K3K MW

Electricity Generation (in GWh)

2012201420162018202005K10K15K20K GWh
Loading...

Utility privatisation

Which segments of the power sector are open to private participation?


Generation
Transmission
Retail

Wholesale power market

Does the country have a wholesale power market?


Available
Not available

Doing business and barriers

Mozambique has historically relied on its large-hydro resources, and the broader power fleet is in need of investment as the country seeks to expand generation capacity to meet rising demand and an ambitious electrification target. Power demand continues to grow quickly, with peak consumption having increased 34% since 2010.

Mozambique’s electrification rate remains low, reaching just 40% in 2021, and progress in extending access to the wider population has been slow. The government is aiming to achieve universal access to electricity by 2030, of which 70% is targeted through grid-connected systems and the remaining 30% off-grid.

The country’s rural electrification agency, Funae, has developed mini-grid and pico-solar pilot programs in partnership with German aid agency GIZ, and signed an agreement with Ignite Power in 2019 to install individual solar energy systems in 300,000 homes in remote areas.

Project development in Mozambique, whether conventional or in mini-grids, remains hamstrung by a lack of regulation. The development of a power plant requires a concession from the government, while the lack of standardization for power purchase agreements (PPA) can result in prolonged negotiations with EDM, which is heavily indebted and undergoing major structural and operational changes. Internal politics at the state electricity company remain a potential challenge to project development.

For on-grid projects, developers can negotiate prices that enable the project to be profitable, but PPAs are negotiated on a case-by-case basis and there is no standardized duration for either on- or off-grid projects.

Developers also face a difficult investment environment in Mozambique. A lack of standardization and clarity around licensing and concessions, the absence of a strong and independent regulator, as well as the challenging position of vertically integrated utility EDM compound a lack of incentives for renewables.

The development of vast offshore gas discoveries does threaten to divert government resources and attention away from renewables. Mozambique’s domestic natural gas sector has grown rapidly since 2015.

Currency of PPAs

Are PPAs (eg. corporate PPAs and all other types) signed in or indexed to U.S. Dollars or Euro?


Available
Not available

Bilateral power contracts

Can a C&I (Commercial and Industrial) customer sign a long-term contract (PPA) for clean energy?


Available
Not available

Fossil fuel price distortions - Subsidies

Does the government influence the wholesale price of fossil fuel (used by thermal power plants) down through subsidies?


Available
Not available

Fossil fuel price distortions - Taxes

Does the government influence the wholesale price of fossil fuel (used by thermal power plants) up through taxes or carbon prices?


Available
Not available

Transport

EV market

The government has yet to implement any substantive policy support in this sector and the electric vehicle market remains at an early stage.

EV policy

The government has yet to implement any substantive policy support in this sector.

Transport policies

Electric vehicle target
Electric vehicle purchase grant or loan incentive
VAT incentives for EV
Import tax incentives for EV
EV charging infrastructure target
EV charging infrastructure support

Fuel economy standards

Does the country have a fuel economy standard in place?


Available
Not available

Buildings

Buildings market

Mozambique has successfully experimented with energy efficiency programs in the past and the government has prepared a new plan to improve energy efficiency through the implementation of energy standards for industrial and commercial lighting.

Energy efficiency policy

Does the country have a national energy efficiency plan?


Available
Not available

Energy efficiency policy

Are there minimum energy performance standards for buildings?


Available
Not available

Energy efficiency incentives

Is there access to loans or grants for energy efficiency measures (i.e. Wall or loft insulation or double glazing)?


Available
Not available

Buildings policy

There are no specific laws.

Buildings policies

Low-carbon heat target/roadmap
Tax credits
Boiler scrappage schemes
Heat pumps purchase grants/loans incentive
Ban on boilers: new build homes
Ban on boilers: all homes

Additional insights
from BNEF

Explore more detailed information on global commodity markets and the disruptive technologies driving the transition to a low-carbon economy.

Read more

Powered by

Energy Transition Factbooks

This marks the 11th anniversary of Climatescope, BNEF’s annual assessment of energy transition opportunities. The project has been expanded to include activity not just in clean power but in the decarbonization of the transportation and buildings sectors.

Climatescope 2022 print report cover

Power Transition Factbook

Download factbook
Climatescope 2022 print report cover

Electrified Heating Factbook

Download factbook

Stay up to date

Subscribe to our mailing list to get the latest news about Climatescope directly in your inbox.


Results
Sectors
PowerTransportBuildings
About
Contact

© 2023 Climatescope. View license and Privacy policy